Santa Clarita officials said this week that they hope to begin work this spring on a long-awaited project to fix a traffic bottleneck on Golden Valley Road as it passes over Highway 14.
The issue currently is that Golden Valley Road is a four-lane road, two lanes in each direction, but cuts down to two lanes on the bridge that runs over Highway 14.
To address the issue, Santa Clarita officials are looking to widen the bridge to four lanes as well, said Harry Corder, a senior engineer for the city and the project’s manager.
“This project has been requested by community members who travel through the area and will greatly improve access to the freeway and surrounding areas,” he said.
The project also includes adding a left turn lane to access the southbound 14 and two left turn lanes to access the northbound 14, Corder said. A sidewalk will also be added to the north side of the bridge, while another protected sidewalk and bike path will be added to the bridge’s south side.
That bike path will be similar to the one that was built as part of the recent project to expand the McBean Parkway bridge between Creekside Road and Avenue Scott in Valencia.
While the anticipated cost for the project is in the neighborhood of $11 million, Corder said the budget is not finalized because the city is still in the bidding phase.
The bidding phase is set to close next week and a contract for the project is expected to come before the Santa Clarita City Council in February, so work could begin in the spring, Corder said.
Partnering with the city are the Los Angeles County Metropolitan Transportation Authority, which is helping fund the project with a $4 million grant, and the California Department of Transportation, whose engineers will provide oversight since the project is within the Caltrans right of way.
Work on the project is currently estimated to take around 15 months, putting completion sometime in the spring or summer 2016, according to Corder. However, that timeline is subject to change depending on how work progresses during construction, he said.
“That is a project that has been a long time in coming,” Santa Clarita Mayor Marsha McLean said Thursday. “We’ve worked very hard to make sure we can get the funding to get that accomplished, and I’m very happy to say that now the funding has been realized and construction is going to be starting soon.”
661-287-5525
On Twitter @LukeMMoney