The estimated bottom line for constructing Castaic High School has been driven upward by increases in the amount of grading and other refinements required since the environmental impact report was approved in 2012, Hart district officials said Friday.
Required changes in grading, hydrology, drainage and the like were detailed in a supplemental Environmental Impact Report for the project, which was approved by the William S. Hart Union High School District last July.
“There were a number of factors that impacted the pad site and the overall project area,” board member Steve Sturgeon said Friday.
One major factor was the increased demand for grading on the site than originally thought.
The 2012 environmental impact report, or EIR, for the Castaic High project called for about 6,310,000 cubic yards of cut and fill for the project.
In the supplemental EIR, those numbers were significantly higher, with 8,778,200 cubic yards of cut and 8,672,400 cubic yards of fill demanded for the project.
“These are things that come up that you can’t necessarily anticipate,” board member Joe Messina said Friday.
Sturgeon, citing a board presentation from last August, said changes in the supplemental EIR added up to an estimated $13 million cost increase for the project.
According to that presentation, the estimated price for the high school project is around $175.8 million.
Recent months have seen plenty of progress in getting the long-promised school built with grading beginning in earnest at the school site in Romero Canyon.
Hart district officials have said the goal is for the school to open with its inaugural class of ninth-graders in 2017.
“The district and the board want to do our very best to keep the project moving forward,” Sturgeon said.