Starting Monday night and continuing through next week, the Highway 14 freeway will be reduced to as little as a single lane in each direction through the Santa Clarita Valley, California Department of Transportation officials said Thursday.
The closures are part of the freeway’s pavement rehabilitation project and will extend from Interstate 5 in the Newhall Pass to Sand Canyon Road in Canyon Country, Caltrans officials said.
Caltrans spokesman Patrick Chandler said up to three lanes could be closed between I-5 and Sand Canyon on both sides of Highway 14. On- and off-ramps for Sierra Highway and Sand Canyon Road are also scheduled to be closed.
The freeway is four lanes in each direction through most of the Santa Clarita Valley.
Plans call for at least one lane in each direction to remain open during construction, but construction could require a full freeway closure at any time during the week, Chandler said.
“We’re going to manage the traffic to keep it flowing so it won’t affect those peak times,” he said.
One to three northbound lanes may be closed for up to 20 hours Monday through Friday beginning at 7 p.m. and finishing at 3 p.m. the following day.
On the southbound side, construction could force one to three lanes to close from 6 p.m. to 5 a.m. the next day Monday through Friday.
Ramps for Sierra Highway and Sand Canyon Road heading northbound are scheduled to be closed 6 p.m. to 3 p.m. the following day. Ramps for the same roads going southbound are scheduled to close 5 p.m. to 5 a.m. Monday through Saturday, April 11.
On Friday, April 10, Caltrans scheduled a 24-hour closure starting at 7 p.m. for lanes on the northbound side of the highway and ramps at Sierra Highway and Sand Canyon Road. Construction would stop at 7 p.m. Saturday.
Chandler said if full freeway closures are required, notices would be provided to media outlets. Motorist could also get updated information by calling 511 or visiting www.go511.com or www.quickmap.dot.ca.gov.
Crews may not require all three lanes for construction, but the closures give crews as much as space as possible for their safety, Chandler said.
He added that Caltrans tries to schedule closures during non-peak hours. He noted that most motorists on Highway 14 experience heavy traffic heading south during morning peak hours and north during evening peak hours.
“We’ve tried to start and finish constructions in the most efficient and cost-effective manner,” he said.
Closures were recently scheduled on the same stretch of freeway but were canceled just minutes before they were due to start.