While workers prepare to pour concrete Friday for the Golden Valley Road bridge-widening over Highway 14, Santa Clarita officials announced a public meeting next Wednesday on another bridge-widening plan, and documents for a third such project were made available to the public.
City officials will outline plans to widen the Lost Canyon Road bridge over Sand Canyon creek at a meeting scheduled 6 p.m.-8 p.m. Wednesday at Sulphur Springs Community School, officials announced Thursday.
The two-lane bridge sits less than 1,000 feet east of the school and is at least 80 years old, city project manager James Tong said. “It’s time for rehabilitation,” he said.
The 50-foot-long bridge is slated to be lengthened by 16 feet and widened to include a trail suitable for multiple uses. Sand Canyon is known for its equestrian trails, and the city recently purchased land in the area under a plan to beef up its trail network on the east side of Highway 14.
“We will be able to accommodate the trail for future and ultimate development of the area,” Tong said.
The bridge construction team is set to begin on the project in late October. Motorists may encounter traffic delays during the estimated 120 construction working days.
Meantime, documents were made available to the public regarding planned widening of the Newhall Ranch Road bridge between McBean Parkway and Avenue Tibbitts near Valencia High School.
The city proposes to widen the bridge over San Francisquito Creek from six lanes of traffic to eight, also adding sidewalks and a bikeway. The upgraded bridge would not only add a lane each direction but also connect the Bouquet Canyon trail that runs alongside Newhall Ranch Road.
The public can view the documents at City Hall room 120 and address comments through July 13 to Monica Heredia in the Public Works Department. The mailing address is 23920 Valencia Blvd. in Valencia, 91355.
Meanwhile, commuters who drive near Highway 14 and the Golden Valley Road bridge overpass will see concrete poured Friday morning for the bridge’s middle support beam.
Construction crews will be “putting up the falsework — that’s the work underneath the bridge that holds up the concrete and the work of the bridge,” project manager Harry Corder said.
Beginning Monday, the Highway 14 freeway will be shut down in both directions during nighttime hours for work on the bridge.
The freeway will be closed northbound from midnight to 6 a.m. and southbound from 11 p.m. to 4 a.m. starting Monday and continuing through Sunday, June 28, according to city officials.