Price tag for Saugus PAC gets heftier — again

Cost increases for the proposed performing arts center at Saugus High School caused heartburn for some Hart district school board members this week.

Board members in the William S. Hart Union High School District approved $279,400 in additional architectural engineering fees for the project this week.

The additional fees are partly a result of changes to the scope of the project, including the addition of a drama department office and boys' and girls' restrooms, according to Wednesday’s agenda.

Some board members, though, seemed caught off guard at the additional costs.

“You come to us, you tell us, ‘The architect is taking a look at it; here’s the price,’ and then from that point on it’s, ‘Oh, we didn’t see this, we didn’t catch this, we didn’t know about this,’ and it creeps up on us,” board member Joe Messina said.

“How do we stop that from happening?” he asked during Wednesday’s board meeting.

The total construction budget for the center is now pegged at $13.5 million, according to information presented Wednesday night.

“It is anticipated that, should the project go to bid within the next two to four months, the expected construction cost will be $13.5 million,” the agenda reads.

An estimate of probable cost for the project was calculated at $10.1 million in 2012, according to documents from Wednesday’s board agenda.

The year prior, the total construction budget for the project had been set at $8,818,000.

“This is really hard for some of us to stomach because we really wanted to control the costs on these auditoriums,” board member Gloria Mercado-Fortine said.

Board members have previously raised concerns about the price tag for the now-under-construction performing arts center at Canyon High School.

The total cost of that center is estimated at $17.6 million, though that “includes everything, from the construction to the lights for the stage and all the furnishings,” according to district spokesman Dave Caldwell.

The two performing arts centers are among the projects included in the district’s $300 million Measure SA bond.

← Back to 2015

About this record

How it was held, read and classified

Record details

Morris ID
140202
System
Morris section CMS (/section/…/article/… and /archives/…)
Reading copy
signalscv.com
Chosen by: only copy held. On this copy: words 335 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 0.
Extracted by
section_cms:articlebody_span
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • url:section_36_local
  • text:valley_names [6 distinct/7 mentions: Saugus, Hart district, William S. Hart, Saugus High, Canyon High]
  • byline:named_writer_no_wire_credit [By Luke Money]
National signals
none fired
Scores
local 8, national 0