Workers jackhammered up concrete and lugged the broken pieces into a waiting loader on Sierra Highway Thursday during construction on a plan to improve traffic circulation around the intersection of Sierra and Soledad Canyon Road in Canyon Country, one of the city’s major intersections.
Work began this week on the beautification and circulation project, which includes changes to the existing medians along Sierra Highway from Via Princessa to Soledad Canyon Road, according to Carla Callahan, an assistant engineer with the city of Santa Clarita.
“We’re going to install concrete pavers in the medians along with the drought-tolerant landscaping and mulch to make it similar to all the other medians within the city,” she said Thursday.
The project also includes installing “purple pipe” to irrigate medians with recycled or reclaimed water in the future, Callahan said.
“So when the water company does make the reclaimed water available, we are ready to hook up and start using that,” she said.
There are also some intersection improvements associated with the project, including installation of a triple left-turn pocket from northbound Sierra onto westbound Soledad.
“By adding that additional turn pocket, we can reduce the signal timing at that intersection and therefore get more cars through that intersection at each signal,” Callahan said. “It will speed up the flow at that intersection.”
The project, which has a budget of about $1.1 million, could involve some lane closures.
Those would be conducted from 8:30 a.m. to 3:30 p.m. along Sierra and from 8:30 p.m. to 4:30 a.m. at the intersection of Sierra and Soledad, according to information from the city.
“We do anticipate this project taking three to four months,” Callahan said. “Hopefully, some time around the holidays we’ll be out of the way.”