A 1.2-mile extension of Via Princessa to Golden Valley Road is expected to cost $50 million.
Another project to connect Dockweiler Drive to Lyons Avenue in Newhall? That’s about a $30 million road.
As Santa Clarita city officials seek to move forward with construction of new roadway segments, linking stretches of thoroughfares planned long ago to join to improve traffic flow citywide, they also face the simple reality that road construction is downright expensive these days.
“Just up front you have the cost of materials — steel and concrete, aggregate,” said Ian Pari, a senior traffic engineer with the city of Santa Clarita. “Those are all very expensive, and they consistently go up year after year. You also have the cost of labor.”
Another cost that comes into play is grading.
“Moving that much earth and doing that much grading is just a very expensive task,” Pari said.
While the city’s estimated roadway construction costs are in line with what you see across the state and nationwide, Pari said the often-rugged terrain of the Santa Clarita Valley makes it “one of the most challenging locations in the immediate area to build roads.”
“Here we have a river and multiple side creeks, railroad tracks, a number of canyons,” he said. “So these are things that have to be either gone over or gone through.”
The challenges are necessary ones, though, because it’s nearly impossible to overstate the importance of transportation infrastructure for residents and commerce, said Victor Lindenheim, executive director of the Golden State Gateway Coalition, during a panel discussion and luncheon hosted by the Valley Industry Association earlier this week.
“Virtually every object in this room — the chairs we’re sitting in, the tables, the tablecloths, the food that’s on your plate — saw the back of a truck,” said Lindenheim, who moderated Tuesday’s discussion. “And the truck, of course, needed a road.”
Financial puzzle
Because of the financial heft that comes with road construction, money usually comes from a number of different sources.
Significant pieces of the puzzle are bridge and thoroughfare fees, which are charged to developers when they build in the Santa Clarita Valley.
Another source Santa Clarita has tapped into is what’s known as the “call for projects” from the Los Angeles County Metropolitan Transportation Authority, or Metro.
“Cities throughout the county put together a list of projects, fill out very detailed applications and submit them to Metro, where they are scored and ranked and prioritized in different categories,” Pari said. “The ones they deem most worthy get funded.”
Through this process, the city has secured roughly $11.5 million for both the Dockweiler and Via Princessa projects, for example.
State and federal funding and grants are also potentially available sources, Pari said.
Despite the cost, there are few who would argue that the Santa Clarita Valley doesn’t need any new roads.
The city is home to about 213,000 residents, and the surrounding unincorporated area is home to tens of thousands more.
The area is also expected to grow in the coming years as new developments add homes and businesses in the area.
As a result, local roads can be jammed at times, and major thoroughfares like Soledad Canyon Road are in need of relief, Pari said.
Focus
Pari said the Via Princessa and Dockweiler projects are the “two we’re probably focusing on now.”
Santa Clarita City Council members voted just last week to certify the final environmental impact report for the Via Princessa extension, which would extend the roadway approximately 1.2 miles so that it meets up with Golden Valley Road.
The council’s vote clears the project to move into the design stage, but that will likely wait until the city secures more funding for the project, Pari said.
The EIR for the Dockweiler project will likely be finalized in early 2017, he added. That road segment would link Dockweiler Drive with Lyons Avenue in Newhall.
661-287-5525