The long-awaited Castaic High School may be closer to reality than ever, but its opening date could still be further away than some have hoped.
Even as construction crews make significant progress in transforming the rugged Castaic landscape into a suitable school site, some William S. Hart Union High School District board members say it may be tough to hit the district’s current projected opening date of August 2017.
Board member Gloria Mercado-Fortine said she thinks that opening date is “not realistic.”
“I absolutely hope I’m wrong,” she said Friday.
Another board member, Joe Messina, also said he thinks opening in 2017 would be tough.
“I really, in all honesty and sincerity, don’t see us finishing it in 2017,” Messina said. “I don’t think 2018 is impossible at all.”
Pushing the opening date back again would represent the latest delay for the high school, which has been proposed for about 20 years to serve the northwestern Santa Clarita Valley and be the seventh comprehensive high school in the district.
Since 2013, the district has moved the targeted opening date from 2015 to 2016 and, most recently, to August 2017.
“I think that’s what has frustrated a lot of people,” Mercado-Fortine said.
Despite the possibility that the school’s opening could be delayed yet again, Hart school board members said last week that they are enthusiastic with how work is progressing.
“I’m thrilled with the progress,” said board member Steve Sturgeon. “Since work started last year they have been working effectively nonstop.”
This drone footage, courtesy of the William S. Hart Union High School District and Romero Canyon LLC, shows the extent of work at the Castaic High School site.
Crews have completed approximately 7.7 million cubic yards of grading at the future school site so far, said Randy Wrage, of Romero Canyon LLC, the developer for the project.
“The site’s just about done,” he said Friday. “We think the grading for the site will be done in December.”
Work also began recently on building a new access road to the site.
Though it took some time to get the necessary permits and permissions to start work on the site, Wrage said construction has proceeded at a good pace since starting.
Looking ahead, the Hart district still has to find a developer and award a contract to build the campus itself, according to district spokesman Dave Caldwell.
It’s not clear when exactly that will happen, or how long that process will take.
Ben Rodriguez, the now-departed Hart district chief operations officer, previously estimated that actually building the campus could take 24 to 26 months.
Should that be the case, Caldwell acknowledged, “it does make it difficult to open a school in August 2017.”
Another factor that could potentially stall the project further is the much-discussed El Nino weather event. Should heavy rains swamp the site during the winter, delays could follow.
“A major factor is going to be what happens in the first quarter of next year with El Nino and how quickly we can progress,” Sturgeon said.
Whenever the school opens, it will do so with an inaugural class of ninth graders. A new grade would be added each year after that until all four grades are on campus.
Since the school will open up with only ninth-graders to start, Sturgeon said an option to speed things up could be to build instruction space for that grade to start with, and continue construction after the school opens.
“If we start with only ninth grade then we need the infrastructure for the entire campus, but we only need buildings to support the curriculum for the ninth grade,” he said. “Construction can continue from that point forward to complete the rest of the campus.”