With the grading of the Castaic High School site complete after 18 months of work, it is up to the William S. Hart Union High School District board to make the next step – choosing a developer.
Supplementary projects for pre-construction work such as laying out electrical wires and completing access roads still have to be finished, however.
The district is working to ensure the project moves forward quickly, and construction could potentially begin as soon as November, said Hart board President Rob Hall.
“I finally feel I can see the path moving forward,” Hall said.
The district expects the completed high school to include classrooms, an administration building, a library, a performing arts center, a multipurpose building, and a physical education building with a gym.
The school site will also have a 5,000-seat football/soccer stadium with a running track, along with basketball and tennis courts as well as baseball and softball fields.
Several of the buildings are being redesigned to account for career technology and information technology revisions since the plans were drawn up. The Hart board voted to approve the revisions, costing $179,100, during its July 20 meeting. The cost will be covered through Measure SA bonds approved by voters in 2008.
Some of the changes include revising classroom layouts and providing enough space for robotics and aeronautics programs and modifying plumbing to account for the nursing and biomedical programs.
Talk of Castaic High School began more than 20 years ago, but the project more or less stalled until it became an election-year issue in 2007, when Gloria Mercado-Fortine and Steve Sturgeon used Castaic High School as a platform for their campaigns for re-election to the board.
Sturgeon said during the campaign that he expected the work to begin June 2008 and finish three years later.
But it was to take a year for the site to be chosen, and delays mounted.
Grading began in early October 2014 and it is unknown exactly when the high school will open. Projections call for the campus to open for the 2018-2019 school year.
Randy Wrage, project manager for Romero Canyon LLC, and his team spent 18 months grading 58 acres of the campus site. Romero Canyon LLC owned the site selected for the school.
Grading was complete in April.
Wrage has been involved with the project since the beginning and said he hopes to continue to be able to work on the project as it moves forward.
“I get almost emotional about it. It’s like having a child almost because it’s been years of toil and effort,” he said.
The Hart district agreed in June to a lease-leaseback option, in which the district leases its property to a developer during the construction period for a minimum of $1 per year. The property is then returned to the district once construction is complete.
Lease-leaseback is controversial because a traditional bid process is not required. It allows the Hart district board members to invite bids from contractors of their choosing.
The board is not bound to choose the lowest bidder under lease-leaseback and can consider who is best qualified for the job, district spokesman Dave Caldwell said.
“Let’s deliver them a high school they can be proud of,” Hall said.