A Castaic landfill that handles much of the garbage from the Santa Clarita Valley is seeking to expand outward and upward as the county landfills inch closer to capacity.
Chiquita Canyon Landfill — near the intersection of Interstate 5 and Highway 126 near Val Verde — currently operates on 257 acres of land but is seeking to increase its capacity to about 400 acres, according to Chiquita Canyon spokeman John Musella.
In addition to expanding over land to the northeast and south, the project would also grow 143 feet in height, although it would still be hidden from the view of Val Verde residents.
“The majority of the landfill extension will be away from the community of Val Verde,” said Musella.
The expansion is necessary because a Los Angeles County Department of Public Works study conducted in 2010 found that there would be a disposal capacity shortfall starting as soon as 2014, Musella said.
“The purpose of the (expansion) is to maintain existing service capacity and provide additional service capacity for the Santa Clarita Valley and the Los Angeles area,” Musella said.
The owners of Chiquita Canyon, Waste Connections Inc., have 693 acres of land surrounding the landfill, said Musella. If the landfill grows to 400 acres, it will be unable to expand any further.
In addition, Chiquita Canyon is also seeking to move the entrance to the facility — along with a few buildings — to Highway 126, said Musella. The landfill plans to build a landscaped berm to screen it from the highway.
The landfill currently accepts non-hazardous wastes and diverts products such as green waste, asphalt, concrete and metal to landfill waste diversion programs, according to information from the Los Angeles County Department of Regional Planning.
The Regional Planning Department has filed a notice of preparation — the first step in the environmental impact review process — and announced last week it would be taking public comments until Feb. 13, 2012.
The comments will be used in the next stage of the process to determine what will be analyzed in the environmental impact review.
Musella said the expansion would add about 25 full-time jobs. The environmental impact review process is expected to take an estimated 18 months, with construction scheduled to begin after that.