County supervisors approved a recommendation Tuesday asking that more money be set aside for continuing road work on Sierra Highway.
The recommendation calls for $41,000 to be added to the contract to widen Sierra Highway between Highway 14 and Pearblossom Highway.
The added cost includes: $2,500 to replace a damaged electrical pull box, $5,500 to move a street light out of a "possible damage" zone and $33,000 to replace a slope damaged by recent rains.
Tony Bell, spokesman for Supervisor Michael D. Antonovich, said the supervisor is working with the Los Angeles County Department of Public Works on ways to improve safety on other sections of Sierra Highway.
"Right now we're in touch with the department on what types of safety to implement," Bell said Tuesday, referring to concerns raised recently over improving Sierra Highway between Vasquez Canyon Road to Caprock Road.