The California Department of Transportation
(Caltrans) will close the following lanes, ramps, and connectors of the Golden State Freeway (I-5) and the Ventura Freeway (SR-134) as part of a
$57.8 million improvement project to construct High Occupancy Vehicle (HOV or carpool) lanes in each direction along I-5 between SR-134 and Magnolia Boulevard. Closures are subject to change. Detours will be signed.
Golden State Freeway (I-5) Closures
Sunday March 11 through Sunday March 18, 2012
▪ Northbound I-5 Connector to Westbound SR-134
TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday March 17th and 9
a.m. on Sunday March 18th)
▪ Southbound I-5 Connector to Eastbound SR-134
TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday March 17th and 9
a.m. on Sunday March 18th)
▪ Westbound SR-134 Connector to Northbound I-5
TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday March 17th and 9
a.m. on Sunday March 18th)
▪ Northbound I-5 Western Avenue Eastbound and Westbound On Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday March 17th and
Sunday March 18th)
9 a.m. to 12 p.m.
▪ Northbound I-5 Western Avenue Eastbound and Westbound Off Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday March 17th and
Sunday March 18th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Western Avenue Eastbound and Westbound On-Ramps
TIME: 7 p.m. to 6 a.m. (Until 10 a.m. on Saturday March 17th and
Sunday March 18th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Western Avenue Westbound and Eastbound Off-Ramps
TIME 7 p.m. to 6 a.m. (Until 10 a.m. on Saturday March 17th and 12
p.m. on Sunday March 18th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo
Avenue Off-Ramps
TIME: 9 p.m. to 6 a.m.
9 a.m. to 3 p.m.
▪ Northbound I-5 Eastbound and Westbound Alameda Avenue Off- Ramp
Time: 8 p.m. to 6 a.m. (Until 9 a.m. on Saturday March 17th and 10
a.m. on Sunday March 18th)
• Northbound I-5 Westbound Colorado Boulevard On Ramp
Time: 10 p.m. to 6 a.m. (Until 7 a.m. on Saturday March 17th)
▪ Northbound I-5 from Colorado Boulevard to SR-134
TIME: Up to two lanes - 10 p.m. to 6 a.m. (Until 7 a.m. on Saturday
March 17th and 9 a.m. on Sunday March 18th)
Three lanes - 11 p.m. to 6 a.m.
▪ Northbound I-5 from SR-134 to Burbank Boulevard
TIME: Up to two lanes - 10 p.m. to 6 a.m. (Until 7 a.m. on Saturday
March 17th and 10 a.m. on Sunday March 18th)
Three lanes 1 a.m. to 6 a.m.
▪ Southbound I-5 from Burbank Boulevard to SR-134
TIME: Up to two lanes - 10 p.m. to 8 a.m. (Until 9 a.m. on Sunday
March 18th)
Three lanes -2 a.m. to 6 a.m.
About the Project
This project is building a high occupancy vehicle (HOV) lane in each direction along the Golden State Freeway (I-5) between the Ventura Freeway
(SR-134) and Magnolia Boulevard in Burbank, a total distance of 5.4 miles
(2.7 miles in each direction). It is also constructing sound walls and retaining walls.
The new HOV lanes will alleviate congestion, encourage carpooling, improve air quality, provide a smoother ride for motorists, and reduce traffic on city streets.