Henry Mayo Newhall Memorial Hospital's four-year, $30 million earthquake retrofitting project is right on schedule, according to spokespersons for the hospital and the general contractor refurbishing the health care facility to meet state-mandated seismic standards.
Lisa Foust, president of the HMNM Health Foundation and Channing Licon, C.W. Driver project manager, discussed the project's progress-to-date and additional planned renovations. C.W. Driver is the contractor in charge of the refurbishing.
"This communication plan is important," said Foust. "We can let the community know what's being done and help direct our patients and visitors within the hospital."
With funding from the Federal Emergency Management Agency, the hospital's earthquake insurance carriers and hospital reserves, the braced frame retrofitting project was designed to meet seismic standards mandated by Senate Bill 1953.
Enacted Jan. 1, 1995, SB 1953 requires that all hospitals with acute-care inpatient facilities be in substantial compliance with the Alfred E. Alquist Hospital Facilities Seismic Safety Act by 2030.
Additionally, hospital buildings posing potential hazards must comply with set standards by 2008 or they will be banned from housing acute care patients.
"The new standards challenged engineers to come up with a better mouse trap," said Foust. "We are very confident that our team of consultants are the best of the best."
Retrofitting work has already been completed on the 1983 addition to the main hospital building and will begin on the original main hospital complex in the next week or two, said Licon.
Some of the retrofitting work completed on the 1983 section of the main building includes the addition of interior and exterior braced frames, repairs of structural damage obtained from the 1994 earthquake and upgraded rest room facilities to comply with Americans with Disabilities Act standards.
The original main hospital complex will also be retrofitted to include earthquake-safe braced framing construction and will undergo earthquake damage repairs as well as numerous other structural upgrades and enhancements. For safety purposes, construction barricades will close off interior and exterior work sites.
The hospital has remained open since the retrofitting project broke ground one-and-a-half years ago, according to Foust. She said they will continue to care for patients throughout the remaining phase of the project, which is scheduled to be completed by December 2000.
"Working in and around patient-occupied space is quite a challenge," said Foust. "But we expected we were going to be challenged and we've taken measures to keep our patients happy."
Noise level testing was conducted to determine the best methods of reducing construction noise throughout the hospital, according to Licon and Foust. As a result, insulation was installed to surround work areas and construction schedules were modified to minimize disturbances to patients.
"We developed slower phasing for the retrofitting, even though it meant increased funding for the project," said Licon.
According to Licon, only two rooms on each floor of the building will be closed simultaneously for retrofitting work. Both Licon and Foust said the spaced construction schedule will allow the hospital to continue to offer it usual full range of services.
"Seismic retrofitting isn't an option; it's imperative," said Foust. "It has to be done."