In the city’s young history, there is perhaps no other series of projects which are as complex as the Golden Valley projects now in the works at City Hall.
The complexity is not only in the projects themselves, but also in the number of agencies, contractors and companies involved, and in the myriad of financing processes involved. When everything is completed over the next few years, here is what these projects will bring us:
• The new Golden Valley High School on 50 acres near Friendly Valley ($10 million).
• Golden Valley Roadway, from Golden Triangle on the north to Sierra Highway with four lanes of traffic, providing alleviation of traffic on Soledad Canyon Road through Canyon Country ($21 million).
• The new Santa Clarita Business Park with 8 million square feet of business/industrial space ($15 million).
• Golden Valley from Sierra Highway to Highway 14 ($5 million). In the future, we are considering a flyover bridge at Golden Valley Road and Soledad Canyon Road, over the railroad tracks ($30 million).
Eastside Economics
It is important to note that in addition to bringing a much-needed new high school to the valley, the Golden Valley projects also bring new business/industrial development to the east side of our city. This is occurring at a time when the majority of this type of development is being done on the west side of our city.
Without assistance from the city and others, it is unlikely that this development would occur this quickly. It is also important to note that the development of the high school is a high priority to accommodate the influx of new students, and the goal here is to open the school by September 2001.
Phase I:
What will Phase I accomplish?
The first phase will entail grading for the Golden Valley High School site and the construction of Golden Valley Road from Via Princessa to Sierra Highway. As a joint project between the city and the William S. Hart Union High School District, and by combining the school’s bid for grading with the city’s bid for roadway grading, both public agencies save hundreds of thousands of dollars.
How Much Will This Cost?
The estimated cost for Phase I for both the school site grading and the road is about $22 million. The city’s portion of this cost is estimated at $11.5 million.
Approximately $7.5 million of this will be paid for through the Eastside Bridge and Thoroughfare District fees collected from developers over the years specifically for this area by both the city and the county. An additional $4 million will come from the city’s General Fund as a loan to the city’s Eastside Bridge and Thoroughfare District. In this way, the city’s loan will be paid back as more developers bring projects into this area.
Why So Expensive?
One of the biggest challenges of this project is the school and roadway site itself. Some of the challenges created by the property include existing underground utilities and gas and phone lines, overhead electrical lines and an L.A. Aqueduct water pipe. As the geological work continues, we have been made aware of ancient landslides, which will need to be re-compacted or buttressed.
Phase I, which is primarily the city of Santa Clarita’s responsibility, also includes designing the roadway, obtaining right-of-way properties, relocation of existing utilities, environmental consulting, road construction and administrative and inspection costs.
Phase II & III
What Will Phases II and III Do and How Much Will It Cost?
These two phases will provide for the construction of Golden Valley Road, from Golden Triangle (near Home Depot) to Via Princessa, with four lanes of traffic. The total cost for construction of this portion of the roadway is $9.5 million. This is being constructed by the developer, Santa Clarita Business Park.
Approximately $7 million of the total $9.5 million will come from Mello-Roos bond financing, which is provided through the city. This type of bond financing was used by the city to help The Newhall Land and Farming Co. finance the public infrastructure around the mall. The remaining $2.5 million will be loaned to the Eastside Bridge and Thoroughfare District from the developer. It will be repaid as future Eastside Bridge and Thoroughfare District fees are collected from future development in this area.
The developer will then utilize an additional $15 million in Mello-Roos financing to help pay for in-tract improvements such as curbs, gutters, sidewalks, storm drains, streets and the like, bringing the total for these phases to $24.5 million.
Future Projects
Studies are under way to determine the type of intersection for Golden Valley Road and Soledad Canyon Road. A determination will be made within a year. We are also working with another development to construct Golden Valley Road from Sierra Highway to Highway 14. This project should also be under way within a year. The extension of Newhall Ranch Road east to Golden Valley Road is also in the preliminary environmental planning stages and should be presented to the city later this year.
Questions?
I hope I have helped you to understand a little bit more about this project. The city will be scheduling a public meeting in the near future to provide a public forum for discussion and information dissemination regarding this project. Thank you for your interest. If you would like more information, contact the city of Santa Clarita at 259-2489 .
George Caravalho is Santa Clarita’s city manager.