Plans for Rio Norte Junior High School are still on hold due to legal review of the West Creek development water supply.
The Sierra Club, Santa Clarita Organization for Planning the Environment, Ventura County and Friends of the Santa Clara River submitted the request for review to the California Public Utilities Commission because they believe the Valencia Water Co. does not have a sufficient water supply to provide both the West Creek development and the school.
West Creek is the 2, 500-unit development proposed by The Newhall Land and Farming Co. located in northern Valencia.
The review is not a legal court trial, but is overseen by a state-appointed administrative law judge.
In spring last year, Valencia Water sent the CPUC letters requesting the West Creek development, which the school is a part of, be annexed into the company’s water service.
The Los Angeles County Board of Supervisors approved West Creek in September, but ceased grading on the land until other water agencies annexed services into the area.
“Sources of water are appropriate for West Creek and north Valencia II,” said Marlee Lauffer, vice president of corporate communication for Newhall Land, owner of Valencia Water.
However, in October the CPUC ordered Valencia Water to conduct more tests until the request for annexation would be granted and then to draft an environmental impact report of its water management plan.
In the meantime, the commission froze all Valencia’s annexation requests, thus the company cannot take on any new customers until the CPUC releases the freeze.
Since then, the William S. Hart High School District, the city of Santa Clarita and Newhall Land have written the commission asking it to separate the school from the review, so grading and construction can begin.
“Currently, the (Hart) school district is housing 6,000 kids in over 200 portable classrooms districtwide,” said Michael Otavka, director of facilities for the district. “Once the school is built— even with no further development— it will be filled.”
Otavka said it takes approximately two years to build a junior high school and fill it with the necessary equipment. Rio Norte will hold 1,200 seventh- and eighth-grade students, he said.
According to Otavka, the school is projected to use 25 acre-feet per year, while homes in the same acreage would use 125 acre-feet per year.
City Planner Jeff Lambert said the city wrote two letters on behalf of the Hart school district to the CPUC to expedite the school site.
Kotch agreed that the school would not be a large water consumer. However, he said, Valencia Water’s mandated water management plan should include the school if the CPUC decides to extract it from the review, a decision the commission has not yet made.
“We’ve got sympathy with the district,” Kotch said. “We don’t want to stand in the way of relieving overcrowded schools.”
SCOPE maintains there is not enough water for the West Creek development and the school.
He said the EIR ruling should be completed by early Spring. If the report is approved by the commission, then the West Creek developing can begin; if the EIR is denied, Valencia Water would have to go through the entire process again, still under an annexation freeze.
“As soon as the water issue is completed, we are in a position to move,” Lauffer said.