Transit Mixed Concrete Co. sent a letter Thursday to the city of Santa Clarita reinforcing what a company official has already said— the size of the project in the city’s counter offer is not a viable alternative.
“As explained in the Feb. 20, 2000 settlement meeting, it is not economically feasible to reduce product sales by 90 percent.” the letter stated. “Limitation of aggregate product sales and elimination of concrete manufacturing capability will not meet the region’s need for construction materials, and will severely prejudice Southdown’s ability to compete in the marketplace.”
City officials confirmed that they had received the letter but declined comment until they had a chance to further review the letter.
A counter offer to Transit Mixed’s first offer had been made by the city last week, one that would have reduced the project to an operation similar to existing operations at the site.
The city of Santa Clarita, the Acton and Aqua Dulce Town Councils and county have been negotiating with Transit Mixed for about two weeks, after a Los Angeles County Board of Supervisors decision forced the two sides to the bargaining table after several months of city-led opposition to the project.
Transit Mixed recently presented the city with a smaller project of, among other changes, a reduction to 69.2 million tons. But the city felt the newest version presented by the company still wasn’t small enough, and now the city is asking for a significantly smaller project— a reduction to 7.5 million tons to produce 5.6 million tons of concrete aggregate.
Brian Mastin, environmental affairs coordinator for Transit Mixed, said the company has already reduced the scale of the mine three times.
The first time was when the project was up for bid in the late 1980s and early 1990s, the company only proposed to mine 56 million tons instead of 100 million tons, which was the amount of the bid.
Additionally, the project was reduced when the Bureau of Land Management approved almost 78 million tons instead of 83 million tons to produce the 56 million tons.
The project was reduced again recently in a smaller mine proposed in the early rounds of discussions with the city that Mastin said cut the project’s volume by 17 percent.
The project as approved in August 2000 by the BLM, which owns the mineral rights to the land, calls for Transit Mixed to mine nearly 78 million tons of material to produce 56 million tons of concrete aggregate, used in home and road construction, from an existing mine.