Berry power facilities reopen

Berry Petroleum Company recently reopened both of its Placerita Canyon cogeneration facilities after Southern California Edison agreed to purchase all of the power generated at the facility and to prepay the company for the power it purchases on a monthly basis.

The company’s two 21-megawatt power plants have been shut down since February and April due to lack of payment for its power deliveries to Edison.

Berry Petroleum also reopened its Kern County power facilities on June 14 after convincing a Pacific Gas & Electric Company bankruptcy judge that its contract with PG&E was properly terminated on April 2.

“We’ve turned the corner,” said Ralph Goehring, senior vice president and chief financial officer of Berry.

“We have been generating almost 90 megawatts of power through our cogeneration facilities since we restarted both our Placerita cogeneration units on June 27, 2001, when we entered into the agreement,” said Jerry Hoffman, chairman, president and chief executive officer of Berry Petroleum, in a written statement.

According to Goehring, several qualifying facilities have been attempting to negotiate with Edison since May. Governor Gray Davis has been encouraging the qualifying facilites and Edison to work out an agreement, he said.

Several other qualifying facilities were able to strike a deal with Edison as well, Goehring said.

“The agreement was approved by the California Public Utilities Commission on July 12, 2001, and became effective by Edison’s notice to Berry, which was received on July 18, 2001,” Hoffman said. “The previously terminated contracts with Edison have been amended to reflect revised pricing, a stay of litigation against Edison which may last as long as 180 days, and other necessary modifications.

“The contracts will continue with their original termination dates— March 2009 for Placerita I and May 2002 for Placerita II. “We believe the amended pricing formulas under these contracts will be positive for Berry and will result in negligible steam cost.

Hoffman also said, “In the last eight months. Our business has been dramatically impacted by the events surrounding the California electricity crisis. These include nonpayment by the utilities for electricity deliveries, the Pacific Gas and Electric Company bankruptcy, political and regulatory uncertainty, litigation issues and uncharacteristically high natural gas prices.

“We believe we have successfully maneuvered Berry through these issues and can now, once again, focus our efforts on developing our reserve base, increasing our oil production and property acquisitions. We will begin our drilling program in August and are planning 10 horizontal wells on our South Midway-Sunset properties, which should have the most impact to our production rate, which averaged about 13,600 barrels of oil equivalent per day in the second quarter.”

Under the terms of the agreement, Berry will be prepaid for each month’s deliveries, according to a written release from Berry. Edison and PG&E owe Berry approximately $27 million combined, plus interest, for power deliveries from November 2000 to March 2001.

The reactivation of the plants, Goehring said, will power about 37,000 homes in Southern California.

“It’s a good thing for the state that producers like Berry are coming back on line,” said Edison Spokesman Glen Becerra. “It adds additional resources for the state to purchase.”

In addition, he said, the added surplus, along with lower natural gas prices and conservation, is aiding the recent decline of energy costs.

The added surplus of energy online, Becerra said, will also help to prevent rolling blackouts in hot weather.

Despite Edison’s money woes, Becerra said, the utility is able to make the forward payments to Berry and some other qualifying facilities because they now have some added income that they did not have several months ago.

Despite the new optimism surrounding the energy crisis, some Santa Clarita residents still aren’t very optimistic.

SCV businessman Wayne Crawford, a member of Santa Clarita’s new Community Energy Advisory Committee, which was formed to serve as an advisory body and to determine the best course of action in solving the energy crisis on a local level, remains pessimistic.

“I feel it’s extremely important for this committee to look into alternatives,” he said. “As long as you’re going to be dealing with Edison, you’re going to be at the mercy of the alliance the utilities have with the Public Utilities Commission.”

Edison, Crawford added, charges its customers more than six times the amount for electricity that it pays for it.

“The city can do a better job for the residents than Edison can,” he said.

← Back to 2001

About this record

How it was held, read and classified

Record details

Morris ID
Not a Morris ID. This record is keyed ts-df:/main/0701/072001b.html.
System
date-file pages (/desk/MMYY/MMDDYY.html)
Reading copy
the-signal.com
Chosen by: only copy held. On this copy: words 735 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 0.
Extracted by
datefile:START_STORY
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • url:v2_datefile_main
  • text:valley_names [3 distinct/7 mentions: Santa Clarita, SCV, Placerita]
  • byline:named_writer_no_wire_credit [By Marci Wormser]
National signals
none fired
Scores
local 7, national 0