The reconditioning, widening and realignment of a section of Railroad Avenue was completed Monday when the street was opened to traffic.
The construction was approved in the latter part of 1995 as part of the Downtown Newhall Improvement project, according to Glenn Adamick, economic development associate for the city of Santa Clarita, with work actually beginning last October.
"The project went really well," Adamick said, "though it went on longer than expected because of the rain (last winter). We lost about 30 days."
Adamick added that "everything's finished, though there are still some minor corrections to be done, some clean-up."
A few businesses in the area hope the "minor corrections" include a close look at the new "No Parking" signs.
"We're not thrilled with that," Diane Vradenburg, assistant manager at Newhall Hardware, said. "We're told they're going away, for the most part, and we hope so."
Jay Thompson, chief steward at Auto Service Plus, said, "Everything looks good and it's pretty beneficial, except for the limited parking. We'll handle 60 to 70 cars sometimes, and it's pretty tight. It's going to become a problem when we get busy."
Thompson added, "The city's done a fine job, it looks great," but noted that the parking crunch could have an adverse effect "on a lot of the businesses."
Vradenburg said the project had already caused problems for Newhall Hardware.
"We lost business," Vradenburg said. "We started closing on Sundays for about a month, but now we're open on Sundays again. It (the expanded road) looks beautiful though, and we hope it's going to continue."