As its last order of business before a new group assumes control next month, the city Planning Commission approved a development proposal by Beazer Homes California Inc. that has been called the build-out of Circle J Ranch in Newhall.
The plan, which was approved Tuesday, calls for 95 single-family residential lots and 156 multi-family units to be built on a 56-area area that borders San Fernando Road and is bisected by Via Princessa. The plan will remove nine oak trees.
The commission eliminated one of the multi-family units because it is too close to the railroad right of way, Planning Manager Jeff Lambert said. Lambert said the average distance for the nine units that will be built close to the railroad is 88 feet.
James O'Malley, a vice president with Beazer Homes, said the developer will be building within a year and should finish the build out, depending on the market, within two years.
"I think the process with the city and the residents was extremely fair and practical," he said. "I think the city provided enough attention to citizens' concerns."
This Planning Commission heard testimony from Beazer Homes on three different occasions and twice this month the development was the only agenda item presented.
The haste was because two commissioners are scheduled to be replaced next month.
Lambert said if a vote was delayed, the new commissioners would have been required to review the tapes of previous testimony as well as the environmental impact report. He said a vote would not have been possible until September or October.
Among some of the agreements Beazer Homes reached with the city was to build a five-acre park, mitigate the noise from the nearby railroad tracks and roadway, mitigate the traffic impacts and reach an agreement with the local school districts.
While Lambert said the project, by installing a 12-foot barrier from the railroad tracks, meets the city's noise ordinance, the commission required an additional noise study to be made before a building permit is issued.
The developer signed an agreement with the William S. Hart Union High School District and has another agreement pending with the Newhall School District.
The proposal was the second Beazer Homes made for the site. The developer originally planned in 1995 to build 348 units, to remove 19 oak trees and to grade on the hillside.