The city's long-delayed Central Park is set for another move forward on Oct. 13.
City director of parks, recreation and community services, Rick Putnam, said that on that date he'll be going to the city council to ask it to award a contract for construction of "phase one" of the park.
The contractor has yet to be named, according to city spokesperson Gail Oritz, but Putnam said the job will go "to whoever gave us the lowest bid."
Phase one, Putnam added, will encompass about 20 acres of the Castaic Lake Water Agency property on Bouquet Canyon Road.
The City and CLWA first signed an agreement to establish the park in 1995. Central Park is planned to eventually encompass 137 acres and a six-lane parkway.
In response to several questions and complaints from citizens at Tuesday night's city council meeting regarding the delays in building the park, Putnam told the council that "a contract for construction of phase one will be presented to the council on Oct. 13, and construction is expected to take 14 to 16 months."
Putnam said later that there were items any developer would have to have in place before actual construction could begin, such as "insurance, bonding, all legal requirements, that usually takes 30 to 40 days," indicating the actual building of the first phase could begin "before the end of the year," Putnam said.
Putnam added that the first 20 acres of the park could be finished "by next winter, at the earliest. If it happens sooner, terrific, but it's contingent on normal weather conditions, supplies, no work strikes, etc."
Putnam said the first 20 acres "will accommodate community recreation needs. There'll be two softball diamonds, two multi-use playing fields, parking and restrooms. American Youth Soccer Organization (AYSO) and Santa Clarita Valley Athletic Association (SCVAA) could make use of it. This is a community park facility, though, open to the public and available to everyone."
The location of the park's roadway is still a point of contention, but Putnam said, "There's no surprise about that. Any road that goes in there is going to cut into the park in some way."
The park, Putnam added, "isn't being designed in a vacuum... We're considering a (road) design which encompasses the entire City Center, that includes CLWA land and Newhall Land property. It's very important to consider alternatives... The reason the road is an issue now is because of a good planning process. Three alternatives are still on the table, as they should be."
Putnam said the perceived delays in getting the park underway are "things that happens in the normal planning process... We've had a number of issues between CLWA and the city which had to be ironed out and discussed: sewer lines, roadway width, well water or not, connection locations for water... Both parties want to make sure it's done correctly. It's just a matter of the process. It's taken longer than anyone would have liked, particularly the city and CLWA."
But once the process moves forward next month, Putnam said, he anticipates the fields can begin to be utilized "between March and April next year."