Hart: Budget 'Out of Our Control'

The single biggest reason costs for two school modernization projects came in $18.6 million over budget is because of "inflation in construction costs which are completely out of our control," said Rory Livingston, assistant superintendent of the Hart district.

The budgets for Arroyo Seco Junior High and Canyon High were set, and then spiraling inflation in the construction industry caused huge increases in cost, he said.

Modernization of the 40-year-old Arroyo Seco is estimated to be $43 million, which is $13.9 million over budget.

Modernization for Canyon High is estimated to be $49.3 million, which includes $4.7 million over budget, Livingston said.

As for who approves all expenditures of money, it is the William S. Hart Union High School District school board, Livingston said. However, the board is not privy to all the day-to-day activities.

"These are (years-) long projects," Livingston said. "They start, stop, there are hiccups. I don't expect the board, or even a principal, to remember everything about a conversation that occurred in 2002."

When principals or teachers request changes, "it lands on my desk," said Livingston. "It happens informally," Livingston said.

He admitted he "acquiesced" to some requests at Arroyo Seco "probably because of the hell of that first summer."

It was "a nightmare," he said, because extensive work was being done while students were on campus. There were no other campuses yet built on which they could have been housed.

Compounding the problem is the school can be accessed from only one side. Everything from people to large construction equipment had to go through the same entrance.

Livingston said another reason for costs spiraling over budget was because of poor architectural work during the first summer of modernization at Arroyo Seco in 2003.

There was "bad work and a bad design," among other problems, he said. The architect "did not do an effective job of scoping the first summer's work and didn't plan for it correctly."

Livingston would not give a cost for the architectural problems but said it is in the millions.

"It's got six zeros behind it," Livingston said. "It is less than 25 percent" of the $43 million project, he estimated.

Asked if the district were suing the architect, Livingston said the district would have that conversation with its legal counsel when Arroyo Seco is completed.

The architect of the first summer of modernization at Arroyo Seco could not be reached for comment.

During the three-year period that Arroyo Seco, Canyon and Saugus high schools have been undergoing modernization, four other schools were built from scratch and have already opened: West Ranch and Golden Valley high schools and Ranch Pico and Rio Norte junior highs. The earliest was begun in 2002, and the latest was opened last year.

Those were over budget as well, Livingston said.

West Ranch and Golden Valley high schools were over budget by $2.5 to $3 million. Rio Norte Junior High is over budget by at least $4 to $5 million. Rancho Pico Junior High is over budget by $8 to $9 million, estimates Livingston.

Budgets are set when planning begins; but again, inflation in the construction industry caused costs to come in millions over budget by the time work took place, Livingston said.

← Back to 2006

About this record

How it was held, read and classified

Record details

Morris ID
Not a Morris ID. This record is keyed ts-ds:31233.
System
displaystory pages (?module=displaystory)
Reading copy
the-signal.com
Chosen by: latest capture. On this copy: words 536 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 0.
Extracted by
displaystory:print_view
signal-extract/0.15 (2026-11-16)

Other copies (1)

Host
the-signal.com
http://www.the-signal.com/?module=displaystory&story_id=31233&format=html
Captured14 November 2006, 18:27:45 UTC
CaptureThe archive does not serve this capture as a facsimile; the text is extracted from it.
SHA-2567109b75dd285d76a5fbae139263c023e09e24dcaaeea0f71bf9813ec30d02becSHA-256 of the bytes the archive holds, recorded at intake. A SHA-1 of the same bytes, taken at the same time, equals the Wayback Machine’s own digest for this capture: G7W7R2FT6MEYS5A4LEOYWHKJZ24GJZB6.
Holds alone
nothing measured beyond the chosen copy

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • text:valley_names [7 distinct/10 mentions: Saugus, Hart district, William S. Hart, Canyon High, West Ranch]
  • byline:named_writer_no_wire_credit [By Bette Keva]
National signals
none fired
Scores
local 5, national 0