Newhall District Renovations Delayed

It has been a busy summer for the Newhall School District, as unforeseen site conditions have delayed the completion of modernization projects at both Newhall and Peachland Avenue elementary schools.

The delays will halt the completion of what Newhall district Superintendent Marc Winger called "new state-of-the-art libraries for each site," forcing the two oldest schools in the district to hold off the first day of school until Sept. 14.

The library construction and other modernization projects - which include renovations of the school's electrical, sewage and water systems, as well as seismic retrofitting - cap the end of a six-year project period made possible by the $35.5 million Measure K bond, which was passed in 1999, and other state-matched funds that brought the project's spending total to $56 million.

"We've done a lot of work," Winger said. "We built the new school and modernized the rest."

Originally scheduled for completion before the start of the school year, both projects hit a series of unforeseen delays and setbacks, resulting in two separate work order amendments for each campus.

At Newhall Elementary, contractors discovered asbestos in a storage building, forcing the removal of the structure at a cost of roughly $40,000. An additional $13,000 was spent for the construction of a new gas line for the school.

Several window frames at Newhall Elementary also were found to contain lead-based paint, which was removed at a cost of about $19,000, while an additional $10,000 was spent to drill out cement, which had been laid in the space above the school's T-bar ceiling design.

"The frames had some lead paint from many years ago," said Michael Clear, the district's assistant superintendent of business services. "It took about a week to drill out all the concrete. You find strange things when you do modernization at an old school."

At the Peachland campus, underground electrical wires had to be rerouted and underground pipes, which also contained asbestos, had to be abated, leading to some additional plumbing work.

After those issues had been resolved, a second work order amendment had to be made after more asbestos and lead-based paint were discovered.

A second work order amendment also was needed at Peachland for the removal of asbestos tiles contained in about 18 classrooms, and the removal of additional window frames that contained lead-based paint.

The overall project budget contained a contingency budget of more than $1.5 million to be used in case such problems arose. Despite the seemingly high costs of the unforeseen construction, only about 18 percent of that money has been spent, leaving the district with a surplus of $ 1.2 million to be used on additional projects.

"We are very under budget, and we're happy about that," Clear said.

Clear added that the superintendent and members of the board were in the process of pulling together a proposed project list.

"There is a whole slew of other projects we want to do," he said.

Although school will resume at Peachland and Newhall elementary schools Sept. 14, construction at the Newhall campus is not scheduled for completion until Oct. 2.

← Back to 2006

About this record

How it was held, read and classified

Record details

Morris ID
Not a Morris ID. This record is keyed ts-ds:32173.
System
displaystory pages (?module=displaystory)
Reading copy
the-signal.com
Chosen by: only copy held. On this copy: words 514 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 0.
Extracted by
displaystory:2007_font_head
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • text:valley_names [2 distinct/9 mentions: Newhall, Newhall School District]
  • byline:named_writer_no_wire_credit [By Jesse Munoz]
National signals
none fired
Scores
local 4, national 0