A segment of the city's cross-valley connector seems almost completed but October might be the earliest the road is open - if there's no heavy rain or bad weather to delay construction.
The approximately 1 1/2-mile extension of Newhall Ranch Road from Highway 126 to Copper Hill Drive still has curb and gutter work, landscaping and street light and signal installations until it is functional, assistant city engineer Curtis Nay said.
"There's still quite an amount of work to be done," Nay said.
About a million cubic yards of earth was graded to make way for the planned connector that can be seen with overhanging electrical wires running to a nearby Southern California Edison facility.
Other unfinished work includes road striping, sidewalk construction, paving and the completion of a bike trail, Nay said.
More earth also needs to be removed.
"In between there's still a lot of grading that's got to get done," he said.
Newhall Ranch and Golden Valley roads comprise the cross-valley connector. City officials say the road, with a projected price tag of $230 million to $245 million, will alleviate east-west traffic throughout the city.
Newhall Ranch Road is set to be completed east of Bouquet Canyon Road into The Newhall Land and Farming Co.'s planned River Village development.
A bridge over the Santa Clara River from the River Village development area to the Golden Valley Road bridge over Soledad Canyon Road is another segment of the road yet to be built.
Senior traffic engineer Ian Pari has said traffic volume on Soledad Canyon Road is projected to "drop by almost half" once the cross-valley connector is completed, providing a direct route from Highway 14 to the Highway 126/Interstate 5 junction.