Three of the Hart district's four new construction projects are behind schedule and some schools will have to wait another full year before construction can begin, according to a district report released Wednesday night.
The insides of Golden Valley and West Ranch high schools' auditoriums were supposed to be completed this year, but now are not expected to be done until November 2008.
For the last eight months, there has been no construction activity on either auditorium, and while the outside of the buildings are complete, the inside is still missing a stage, carpeting and seats.
The schools were built with state-regulated "hardship funds," and the Hart district had to wait an extended period of time between building the schools and putting up expensive additional buildings, said Mike Otavka, director of new construction for the district.
"The best time in practicality ... was we would wait until both (Golden Valley and West Ranch schools' main buildings) were completed to complete the work," he said during his presentation.
However, by the time the school was eligible to proceed, funding was a major concern for finishing the auditoriums at the schools.
Specifically, the William S. Hart Union High School District was short about $900,000 of the total $3.42 million needed to complete the jobs. However, now district officials have found that money, they said.
Rancho Pico Junior High School's gym is costing about $400,000 less than expected and it may be possible to have the state reimburse roughly $500,000 worth of construction at Valencia High School's new JROTC building, said Rob Gapper, chief operations officer for the district.
"We believe that by the time this project is bid, we'll have a plan to properly fund it," he said.
Still, the projects must be approved through the Department of State Architects - a process that typically takes six months, though it has been suggested that the auditorium projects may take half that time - pushing the date the project goes out to bid until February 2008.
Once the bid is accepted, construction is expected to take six months, according to district documentation.
Rancho Pico's gymnasium is an additional late project.
Having been under construction since last year, it was expected to be completed by April 27.
However, documentation presented Wednesday showed the work to be only 67 percent complete.
The problem was tied to a single contractor who has not been doing the work required, Otavka said.
"(The gymnasium) is still planned to open before school starts," Otavka said.
So is Valencia High's JROTC 3,870-square-foot building. It is set to be finished on time by June 21.