The state has resumed pumping at a major State Water Project pump, at levels higher than normal to make up for lost time.
The Department of Water Resources on Monday began pumping more than 6,600 cubic feet per second - 2,600 more than average for this time of year - at the pumps that deliver State Water Project water to Southern California.
"This would be about the highest level we would go," said Ted Thomas, spokesman for the DWR. "We're sort of making up for lost time."
The pumps had been shut down for 10 days in June and were in limited operation for several weeks due to concerns about the declining number of the delta smelt, most of which have now migrated away from the pumps to cooler water.
"At this stage of the game, it's almost business as usual," said Dan Masnada, general manager of the Castaic Lake Water Agency. "They should be able to pump essentially at normal levels, which is certainly a relief to us because that will preserve our ability to receive our allocation of 60 percent of our contract amount for this year, which would have been in jeopardy if the pumps had been shut down into July."
The pumps are pumping at increased levels to replenish the state water supply south of the delta, he said.
"Because San Luis (Reservoir) is drawn down and we've basically been taking water out of storage, the reason they're pumping above what is typically seen as normal is not just to meet demands, but also to fill up the downstream storage that was in part depleted as a result of the shutdown during June."
Because of ongoing litigation concerning the permits for pumping in the delta, the state will go about getting the appropriate permits over the next year.
"We may be in the same boat again next year," Masnada said. "Once they get the permit, the new rules will be established and they will have the parameters and they will know for certain what they can and can't do. They want to do it in a manner that truly protects the species but that doesn't result in an unnecessary reduction in delivery of State Water Project supplies to CLWA and all the other State Water Project contractors in Southern California."