In less than two months, College of the Canyons will become a college with two campuses. For that vision to truly become a reality, modular buildings must first be placed on their foundations and a number of final on-site traffic and utility hookup modifications made before opening for classes Aug. 27.
"It's moving along pretty good," said COC Dean of Facilities Jim Schrage of construction at the 70-acre site located at 17200 Sierra Highway in Canyon Country, less than two miles from Soledad Canyon Road.
According to Schrage, the roughly $34 million Canyon Country campus construction project - funded by Measure M, the $160 million general obligation bond that voters passed last November - is nearly complete, with the college's final utility plan and traffic proposal submitted for county approval, and the first wave of modular buildings set to be installed Tuesday.
"That was our last major hurdle," Schrage said about the college's impending approvals.
Although the traffic plan had to be submitted to county engineers four times in order to iron out problems created with the establishment of a widened road and additional traffic signals and crosswalks, Schrage said campus utilities hookups are nearly complete and ready to be wired into the initial set of 23 modular building classrooms and additional lab and facility spaces expected to be installed by Aug. 1.
Water lines have already been connected to the north side of campus, with connection to the south side of campus expected next week, Schrage said. In addition, campus gas line hookups are expected within the next two weeks, with electric lines set to be run under Sierra Highway and connected to the campus in about the same time frame.
"We're ready for them. I'd say by the third week of July we should have power," said Schrage, adding that cable lines were already on site and phone lines are expected in mid-August. "(Phone lines) are the only thing that's lagging right now."
Although things are "looking good" for the highly anticipated Aug. 27 fall semester start date, the construction team had to overcome a number of setbacks first encountered during the grading process that began last July.
Soon after bulldozers began reshaping the earth, a number of ancient landslides far beneath the site's surface were uncovered - which forced delays as engineers sought to rearrange the soil to stabilize the ground below.
Although Schrage estimated that the setbacks delayed the project by about three months, he said that the efforts by the project's team of engineers and designers helped stave off extra costs and keep construction on track.
"We ended up doing a lot of design build at the end," said Schrage, describing the process in which engineers would improvise the original design concepts to accommodate the adjusted land grading.
"It could have been a lot worse," Schrage said. "We could be a year behind right now if we didn't have the team that we have right now."