The city of Santa Clarita on Wednesday applied for $54 million in federal funding for the completion of the cross-valley connector.
City officials submitted the application through U.S. Rep. Howard “Buck” McKeon, who in turn will include the project in a list of proposals for funding under the reauthorization of the Transportation Equity Act for the 21st century.
Reauthorization of the act occurs every six years to provide federal funding for surface transportation programs for highways, highway safety and transit.
If approved, the city — under the best-case scenario — would begin receiving funding as soon as next year, said city transportation official Mark Yamarone.
He said the application is the first part of a two-step process. The city first needs to be included in the legislation before it can try to receive any funds over the six-year period, beginning in the fiscal year 2004.
The cross-valley connector is the planned 8.5-mile road intended to serve as the main east-west artery through the SCV, connecting Interstate 5 to state Route 14.
The city had hoped to receive about $8 million in federal funding for the road last month, but it failed to make a list of projects for the federal spending plan approved by Congress.
That money is included in the city’s new, $54 million request, Yamarone said.
Connie Worden-Roberts, chairwoman of the SCV Transportation Alliance, said the road continues to be the city’s No. 1 priority.
“Hopefully (the application) was submitted in time to hit the window of opportunity,” she said.
The portions of the road that still need to be constructed are from Bouquet Canyon Road to Soledad Canyon Road, the Newhall Ranch connection to state Route 126, and the bridge to connect the two road segments over the Santa Clara River.
Alignment of the road over the Santa Clara River is a project that would exceed the city budget, Worden-Roberts said.
The $54 million includes the opening of the remaining portions of the road, as well as the widening of existing portions to six lanes from four.
“(The money is) more than what we need to open the road,” Yamarone said.
Yamarone said in addition to funding for the cross-valley connector, the city asked for $7 million for new buses and $5 million for the future expansion of the Transit Maintenance Facility.
“If (McKeon) can assist us in doing this, we’ll think he can walk on water,” Worden-Roberts said.