From new doors to new buildings, Leona Cox Community School is undergoing extensive renovation and modernization thanks to state bond money.

The $6 million project, which began in December, is expected to be completed by October when school will open. It is funded entirely by the state through Proposition 47 and hardship funds.

What makes Leona Cox’s expansion so unique is a two-story building placed into the side of a slope that divides the 40-year old campus in half.

To maximize the 10-acre campus, engineers cut away a portion of the hillside to place a two-story, 12-classroom structure that will have access from the bottom and the top floors. A walkway will be placed on the second level for students to use as access to the top floor and an elevator will transport disabled students.

With this new building, the school will have the capacity to add 250 students to its current population of 530.

“Taking the hillside and taking the challenges with it has maximized the school site,” said Assistant Superintendent Kent Frison. “Excess dirt was removed from the site and transported to another school site in Sun Valley.”

On the upper field, a multi-purpose room is under construction with an outdoor amphitheater, teacher lounge and kitchen. Temporary portables will be removed to allow for a renovated playground area.

The administration building, library and parking lot are being expanded. New landscaping and hardscape will enhance the look of the entrance to the school, Frison said.

Besides the new doors, older classrooms will get new cabinets, carpets, walls and sinks. The outside of the classrooms will be painted green to coincide with the school colors of green and gold.

Having construction crews and heavy equipment on campus has been challenging, said Principal Marianne Hamor, but the students have been fascinated by the process.

“Living through this, when you see day-to-day changes, makes it worth it,” Hamor said. “The community has been so supportive. It’s not just a promise anymore. They get to see changes daily.”

The students have been extremely patient, she said. To make up for the lack of playground space during construction, the students got together and came up with ideas to keep kids busy during recess.

“We’ve been creative,” Hamor said. “We brought out portable volleyball nets and game carts. Our students still participate in intramural basketball games, but practice on a half court. They’ve been doing OK.”

The expansion of Leona Cox and the expansion and modernization of Mint Canyon Community School in the near future will give all students in the Sulphur Springs School District some breathing room, said Teresa Todd, a school board member and parent of a child at Leona Cox.

“The kids have still been on campus during construction and the teachers are teaching. It’s been amazing,” she said.

Image not recovered042103cox.jpg

← Back to 2003

About this record

How it was held, read and classified

Record details

Morris ID
Not a Morris ID. This record is keyed ts-vs:2265.
System
ViewStory pages (/News/ViewStory.asp)
Reading copy
the-signal.com
Chosen by: only copy held. On this copy: words 467 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 1.
Extracted by
viewstory:font_body
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • text:valley_names [2 distinct/2 mentions: Mint Canyon, Sulphur Springs]
  • byline:named_writer_no_wire_credit [Patti Rasmussen]
National signals
none fired
Scores
local 4, national 0