Caltrans: Toughest part of reconstruction complete

The most difficult aspect of a three-year, $45.3 million reconstruction project to replace the Interstate 5-Magic Mountain overpass and the Santa Clara River bridge is almost complete, transportation officials said Wednesday.

Stage 2 of the replacement project, temporarily reducing the number of freeway lanes on I-5 from four lanes to three on each side while the center of the Magic Mountain Parkway overpass and Santa Clara River bridge are replaced, is scheduled to be complete in October, said Jagdish Patel, the California Department of Transportation’s senior resident engineer for the project.

Patel said the building of the middle portions of the bridges, which began in July, was the most difficult aspect of the project because of limited access amid the traffic.

“It is a challenge since the I-5 is a major corridor and we are trying to minimize the impact to the motorists,” Patel said during a tour of the construction area Wednesday.

“Because of the traffic on either side of the construction, it is difficult for the contractor to move cement trucks into the area,” he said. “We have to close a lane on the freeway to get a truck in.”

Patel, who has worked for Caltrans since 1991, said despite the challenges, the project is moving ahead on schedule and there have been no significant accidents on the construction site.

The replaced center portion of the bridges is expected to be finished in October; Stage 2 is scheduled to be completed next March.

Caltrans design engineer Gregory Farr, said the Santa Clara River bridge is being replaced because of damage caused by erosion. He said the Magic Mountain Parkway overpass is being rebuilt to improve traffic capacity.

Stage 3 of construction, scheduled for completion in March 2005, involves the replacement of the other side of the overpass and bridge, with north- and southbound freeway lanes remaining at six but moving to the center of the freeway.

The northbound on-ramp at Magic Mountain Parkway will be closed until January.

Caltrans spokeswoman Jeanne Bonfilio said the construction project has gone better than the department had expected.

“We really feel traffic congestion throughout the construction zone has gone better than we anticipated,” Bonfilio said. “On the first day of the Labor Day weekend, the longest delay on the freeway was two and a half minutes.”

Yet on Monday, the last day of the Labor Day weekend, Bonfilio said the longest delay on the freeway was more than 30 minutes.

“We have to work on doing a better job getting the message out to returning motorists,” she said.

← Back to 2003

About this record

How it was held, read and classified

Record details

Morris ID
Not a Morris ID. This record is keyed ts-vs:2569.
System
ViewStory pages (/News/ViewStory.asp)
Reading copy
the-signal.com
Chosen by: only copy held. On this copy: words 426 (e-mail addresses counted as one token); reader comments 0 (counted, not reproduced here); images 0.
Extracted by
viewstory:font_body
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • text:valley_names [1 distinct/4 mentions: Magic Mountain]
  • byline:named_writer_no_wire_credit [Brian Franks]
National signals
none fired
Scores
local 4, national 0