For the next three years, motorists can expect two- to 30-minute delays on Interstate 5 throughout the Santa Clarita Valley as part of a reconstruction project to replace the Magic Mountain Parkway overpass and the Santa Clara River bridge, transportation officials said Thursday.
Currently, the California Department of Transportation estimates motorist travel time on I-5, during peak hours between Hasley Canyon Road and Lyons Avenue, to be about seven minutes. In early June, when stage 2 of freeway reconstruction begins, Caltrans estimates the travel time will increase to nine minutes during peak hours, more than 15 minutes on weekends and more than 30 minutes on holidays.
“We understand there will be frustration in the beginning,” Caltrans spokeswoman Jeanne Bonfilio said at a community open house Thursday evening. “We will be monitoring traffic during the duration of construction with the California Highway Patrol to do what we can to help move traffic along.”
Bonfilio said The Old Road is the suggested alternate route during periods of heavy I-5 congestion and that the speed limit on the freeway has been reduced to 55 mph throughout the construction zone, south of Hasley Canyon Road to north of Valencia Boulevard.
Caltrans said traffic will increase on city streets because of the reconstruction project, and that the widening and lengthening of The Old Road between Magic Mountain Parkway and Lyons Avenue is scheduled to be complete Aug. 15 to minimize some of the expected traffic.
C.C. Meyers of Orange, the contractor on the I-5 reconstruction projects, is currently replacing freeway shoulders on north- and southbound lanes — stage 1 of the project.
Once completed, freeway lanes will be reduced from eight north- and southbound lanes to six, while one side of the Magic Mountain Parkway overpass and Santa Clara River bridge are replaced. Construction is expected to be completed in March 2004.
Stage 3 of construction, which is scheduled to be completed in March 2005, involves the replacement of the other side of the overpass and bridge, with north- and southbound freeway lanes remaining at six.
The Magic Mountain Parkway 1-5 northbound on-ramp will be closed for the duration of the construction.
Traffic from the Valencia Industrial and Commerce Centers will be diverted to The Old Road with the southbound Rye Canyon Road on-ramp metered for three years as part of the project.
Bonfilio said the Santa Clara River bridge is being replaced because of damage caused by erosion and that the Magic Mountain Parkway overpass is being rebuilt to improve traffic capacity.
Caltrans said signs will be posted to assist motorists with other possible intermediate closures during the reconstruction projects, and that all closures and schedules are weather-permitting and subject to change.
“Try not to take the freeway for the short trip,” Bonfilio said. “It all adds up and does make a difference.”