City officials are bracing themselves today for the possibility that a settlement will be announced between the county of Los Angeles and Cemex, the Mexican cement giant that wants to mine millions of tons of sand and gravel in Soledad Canyon.
The supervisors will discuss the county-Cemex litigation today behind closed doors.
Gail Ortiz, spokeswoman for the city of Santa Clarita, said City Council members will be on hand just in case a settlement is announced.
“Council Member Laurene Weste will testify (today) to urge the board (of supervisors) not to settle until legislation (by U.S. Rep. Howard “Buck” McKeon) has gone through,” she said. “And if they do settle, we hope they include the 13 mitigation measures that are important to the community.”
The city, which has spent more than $2 million fighting the project, has compiled a list of provisions, including using rail-haul to reduce or eliminate gravel truck traffic on state Route 14 and Interstate 5; import water from the project instead of pumping from Santa Clara River; and to leave ridge lines alone.
County officials remained tight-lipped about the case Monday, citing a gag order issued by U.S. District Court Judge Dickran Tevrizian.
Deputy County Counsel Richard Weiss said all discussions are confidential.
“We just can’t talk about what’s going on with the case,” he said.
Asked if the meetings between county and Cemex were productive, Weiss simply said, “Both parties have met more than the 24 hours” — a requirement Tevrizian had imposed on June 16.
Cemex spokesman Brian Mastin could not be reached for comment.
The federal government issued two 10-year permits to Cemex’s predecessor in 1990, giving it the green light to extract 83 million tons of gravel over 20 years on the 460-acre site, south of state Route 14 on Soledad Canyon Road. The mining plan was later reduced to 78 million tons of raw materials, which would produce 56.1 million tons of concrete aggregates used in housing and road construction.
Cemex sued the county when the board of supervisors voted unanimously to deny the necessary environmental permits, and the U.S. Department of Justice joined the lawsuit on Cemex’s behalf.