Attorneys will wrangle Sept. 8 and 9 over a plan by Remediation Financial Inc. to encumber the 989-acre Bermite property so it can take out a $7.5 million loan while in bankruptcy.
The financing plan has drawn fire from Whittaker Corp., which is responsible for cleaning the property of toxins left behind after decades of weapons-making, and by Steadfast Insurance Co., which is paying for much of the cleanup.
The two companies worry that a further encumbrance on the property in central Santa Clarita could hinder their chances for payback. Whittaker says RFI shares the cleanup responsibility, while Steadfast says RFI owes it $41 million.
RFI says it should be allowed to take out the $7.5 million loan from First Credit Bank of West Hollywood because the Bermite property is potentially worth $214 million if developed for homes, and RFI owes only $116 million to secured creditors, leaving $98 million in available equity.
Last week, Judge Charles G. Case of the U.S. Bankruptcy Court in Phoenix shot down RFI’s bid to take out the loan on an emergency basis. In lieu, Whittaker and other creditors agreed to lend RFI $97,452.62 so it can pay salaries and expenses through Sept. 15, by which time the court will have decided on RFI’s loan request.
Both the Castaic Lake Water Agency, which has a pending lawsuit against Whittaker and RFI to pay for the cleanup of contaminated groundwater, and the city of Santa Clarita, which is seeking to take RFI’s Metrolink parking lot and Golden Valley Road properties through eminent domain, have teams of attorneys representing their various interests in the bankruptcy court.