Wooden power poles on both sides of Soledad Canyon Road between Camp Plenty Road and Sierra Highway are being removed and replaced with underground power lines in a $5.5 million Canyon Country beautification project that could continue through spring 2005.
Lanes are periodically closed for public safety, and Sgt. Jim Anderson said the Sheriff’s Department is stepping in to relieve traffic congestion as needed.
“When there’s going to be an extended delay because of lane closures, the city notifies the Sheriff’s Department,” he said. “Deputies working overtime, or volunteers, are doing traffic control.”
The project will be done in two phases. Phase 1, which started in early July, is expected to take four months to complete, said Juan Ramirez, project manager for the city of Santa Clarita.
Most of the work is performed between 8:30 a.m. and 3:30 p.m., he said.
Metal plates are sometimes overlaid on the road, but due to safety concerns over the sandy soil underneath some sections, multiple lanes are periodically closed.
“When we’re working in the intersections, we close multiple lanes for safety,” Ramirez said. Lane closures “will vary from time to time. All the major intersections will be done at night.”
The major intersections on Soledad are at Camp Plenty Road, Whites Canyon Road, Crossglade Avenue, Luther Avenue, Vilna Avenue and Sierra Highway.
The bulk of the project is funded by Southern California Edison under monies set aside for beautification.
“We’re happy to participate with the city as a partner on these types of improvements,” said Southern California Edison spokesman Glen Becerra. “You have a very proactive city here. They do a lot to make sure all areas of the community receive improvements.”
The city has budgeted $100,000 to pay for panels and meters for some businesses which will need to be converted to an underground electrical feed, Ramirez said.
Phase 2, expected to start around November, will be more complex, he said. The city will request easements from some residents to relocate power poles. Affected areas may include the residential side of Soledad between Whites and Crossglade, and near Luther and Vilna. Ramirez said this phase could take four to six months.
After the wooden poles are removed, they will be replaced by the city’s standard street lights mounted on concrete poles.