The Santa Clarita Valley Missing Link has been found ... or at least constructed.
The Newhall Land and Farming Co. officially opened the 1-mile stretch of The Old Road between McBean Parkway and Valencia Boulevard, allowing for an uninterrupted north-south corridor that parallels Interstate 5. The road opened to all traffic around noon Thursday.
“We are standing in what has been called ‘The Missing Link,’” Newhall Land Chief Executive Gary Cusamano said at the opening ceremonies Thursday. “We’re going to be able to eradicate that vocabulary from the Santa Clarita Valley.”
The $14.8 million road is a part of Newhall Land’s Westridge project, and was fully funded by the landowner.
Cusamano said the yearlong project was completed on time and under budget.
U.S. Rep. Howard “Buck” McKeon and Los Angeles County Supervisor Michael D. Antonovich joined Cusamano, Santa Clarita Councilman Cameron Smyth and Councilwoman Laurene Weste for the inaugural ride in the back of a horse-drawn carriage.
“This is a vivid example of public-private partnerships working together,” Antonovich said. “It works and we need to have more of it.”
The supervisor said he was glad Newhall Land completed the road prior to the construction homes to allow for it to be used as a detour during the I-5 construction at Magic Mountain Parkway.
Smyth said although the road is outside city limits, it still plays a pivotal part in alleviating traffic on city streets.
“This road is going to benefit thousands of city residents,” he said.
Westridge is scheduled to begin construction in October. The complex includes a golf course and 1,700 executive and custom single-family homes, as well as townhomes and apartments. A retail center will front the development facing The Old Road.