Construction on the cross-valley connector has been delayed for about a week by recent storms, officials said Wednesday.
Both segments of the 8 1/2-mile project under construction have been affected.
“When it’s raining all day it’s not a work day,” said Chris Price, assistant city engineer for the city of Santa Clarita.
But rain delays are expected at this time of year, and the temporary hiatus will not have a major impact on the project’s schedule, he said.
The cross-valley connector is a roadway that will connect state Route 14 with Interstate 5 at Highway 126, giving motorists an alternative to Soledad Canyon Road for crossing the Santa Clarita Valley.
One section under construction, between state Route 14 and Sierra Highway, has only about 20 more feet to go. D. H. Horton is building the segment as required under a development contract with the city.
The other section is a bridge being built by the city over Soledad, Golden Triangle Road and the railroad tracks near Saugus Speedway.
Construction crews are drilling holes and filling them with concrete and steel, which will serve as the foundation for the bridge approach for the Golden Valley Road interchange.
The entire project is expected to cost $245 million.