The clock has stopped ticking on a proposed project that could route a natural gas pipeline through the Santa Clarita Valley because the license application was found to be insufficient.
Because of possible impacts within the Santa Clarita Valley, city officials sent a comment letter to the State Lands Commission on Dec. 20. The letter concluded a preliminary study on the proposed pipeline through the SCV had not fully explored potential effects.
The city strives to ensure natural resources, including the Santa Clara River, are protected, Kai Luoma, a senior planner for the city said earlier.
“We feel the inadequacies found in the (draft environmental report) can be addressed and overcome,” Luoma said.
In a letter dated Jan. 5, the Coast Guard and Maritime Administration notified Global resources company BHP Billiton further information is needed for review of the project.
Areas of concern are pipeline routes, public safety, noise, air and water quality, biology, and proximity to schools.
“I believe the clock will be stopped for two to six months,” said Cy Oggins, a staff environmental scientist for the California State Lands Commission.
The city’s comments and the commission’s response to them will be included in the project’s final environmental report.
If the project has not been halted, it would have come before the commission the first week in March.
The length of the suspension will depend on how quickly the applicant submits the requested information, said Lt. Ken Kusano, program manager for the U.S. Coast Guard.
The U.S. Coast Guard, the U.S. Maritime Administration and the California State Lands Commission are conducting an environmental review of the proposed project in adherence with federal and state laws and guidelines.
Billiton has proposed to build an offshore floating storage and processing unit that would be anchored 14 miles off the Ventura County coast. Underwater natural gas pipelines would come inland in Ventura County. An onshore pipeline that could be routed through Santa Clarita would move additional supplies into the Southern California Gas Co.’s system.
Liquefied natural gas would be delivered in tankers to the offshore site, where it would be processed into natural gas.
While the Gas Co. would benefit from the project, Billiton is the sole applicant.
On Nov. 29, the three governmental agencies hosted a hearing and open house at City Hall to provide information and seek input on the project. Officials, residents and a mix of business interests spoke out.
Citizens will have another opportunity to comment on the project before the federal and state agencies take action.
The Southern California Gas Co. has touted the project’s potential benefits.
A research study has indicated “total savings in gas costs from bringing LNG into the West Coast will be at least $700 million dollars a year, and could be as much as $1 billion dollars a year,” Tony Tartaglia, a spokesman for the utility, said earlier.
Billiton is offering to pay for the entire cost of the pipeline on shore, and no costs would be passed on to the Gas Co.’s ratepayers, Oggins said.