City officials helped build the cross-valley connector Tuesday night without manning any heavy machinery. They awarded a design contract for a bridge that forms a piece of the roadway and OK’d moving two pipelines that block the path of another section of the road.
The pipelines snake under a spot designated for an eight-lane stretch of Newhall Ranch Road, between the Interstate 5-Highway 126 Interchange and Rye Canyon Road. This segment of the connector is called the gap closure.
“I think this particular project will make a huge difference in relieving congestion on several different roadways in the city,” said Assistant City Engineer Curtis Nay. “Roads like Magic Mountain Parkway, Valencia Boulevard and McBean Parkway.”
Nay estimated this piece of the $245 million east-west roadway will cost $27 million. Construction is expected to start in early fall and should take about a year, he said.
Santa Clarita officials have made traffic their top priority and look to the 8.5-mile cross-valley connector as a route to smooth the commute from Valencia to Canyon Country and from Interstate 5 on the valley’s west side to state Route 14 on the east.
The city will pay Arco Midcon LLC $500,000 and Pacific Pipeline System LLC $650,000 to move their pipelines. These are among several utility relocations deemed necessary to make room for the roadway.
Several funding sources will be tapped for the $27 million tab, including developer fees, $6.2 million in Proposition C funds and an additional $3.4 million in Proposition C funds from next year’s budget.
Santa Clarita City Council members also awarded a design contract for the six-lane Golden Valley Road bridge over the Santa Clara River, which will link a planned extension of Newhall Ranch Road to the Golden Valley Road-Soledad Canyon Road interchange.
The contract, valued at more than $911,000, was nabbed by Dokken Engineering of Rancho Cordova, Calif.
A public hearing on the environmental impacts of the gap closure project was opened, but staff members’ presentation was waived because no community members came to speak on the issue. The project’s final environmental report can be viewed at City Hall. The hearing was continued to the May 24 council meeting.