Santa Clarita City Council members said more information is needed before it will commit to a former lumber yard as the site of the new community center.
A majority of the council has selected the abandoned Anawalt Lumber property, located on Market Street in downtown Newhall, to install a 17,000-square-foot community center. The city purchased the 4.5-acre site in June with a grant it received from the Metropolitan Transit Authority to use for Metrolink parking.
Three possible sites for a permanent center home were presented to the council during a study session Tuesday. Anawalt seemed the most rational and economically feasible to the council.
If selected, the center will share the lot with 150 parking spaces to be used by train commuters.
Mayor Frank Ferry said the tight city treasury would limit the amount spent on purchasing the land, then constructing a facility. At least with the Anawalt site, Ferry said, the construction of a new center isn’t six years away.
“I’d rather spend the $2 million and get a product now,” Ferry said. “There are too many other things that need to get done.”
The other two sites are located off San Fernando Road.
Councilman Cameron Smyth agreed with Ferry.
“It’s pretty clear,” Smyth said.
Preliminary figures show a $2 million budget for a new center.
Interim City Manager Ken Pulskamp said a series of public meetings resulted in a cry for a new facility as soon as possible.
“What we have heard from the community is that we want you to move quickly,” Pulskamp said.
Councilwoman Laurene Weste wasn’t all for the Anawalt site because of its proximity to the Metrolink station and the potential for flooding.
“We want a site that is able to be more diverse,” Weste said. “The basic thing we’re struggling with is economics.”
Some parents agreed with Weste.
“To me, you are putting on a band-aid,” said Rosa Hernandez, whose daughters use the complex. “We’re going to be here again in 10 years.”
Pulskamp said city planners will look at every aspect of building a new center, including making the Anawalt land less susceptible to flooding.
The city wants to begin construction on the new facility by summer, he said.