ArchiveSCV
the-signal.com. The Santa Clarita Valley Signal. Back to the collection.

· signalscv.com, Wayback capture

SCV Sanitation District work halts in face of judge’s ruling

The SCV Sanitation District has found itself stuck between a rock and a hard place — state water regulators are demanding it work to complete its chloride-reduction project and a judge has demanded it stop all work on the project.

Santa Clarita Valley Sanitation District officials have decided to stop all work until they come up with a solution, said district spokesman Bryan Langpap.

“The district is currently analyzing the best options available to comply with the court’s ruling,” Langpap said.

Acting on a lawsuit filed by Santa Clarita Valley residents opposed to the Sanitation District’s chloride-reduction plan, Judge James C. Chalfant ordered the district to revise its Environmental Impact Report.

When it filed a revision to the EIR that simply knocked off the recycled water element, the judge sent district officials back to the drawing board and ordered them to cease all work on the reduction proposal until an EIR is in place that he says meets the California Environmental Quality Act.

“(The district) is committed to complying with the California Environmental Quality Act while doing its best to meet the state-mandated chloride compliance deadline of July 2019,” Langpap said.

Meanwhile, officials with the Los Angeles Regional Water Quality Control Board made it clear they expect the Sanitation District to keep up its timetable to get a chloride-reduction system up and running.

Sam Unger of the water quality board said the Sanitation District is on the right track, and that the recent court decision ordering it to stop all work does not affect the four-year-plan — at the moment.

But each day that goes by with work crews sidelined, bulldozers sitting idle, materials not ordered, grant opportunities missed puts the district behind schedule.

“The scheduled benchmarks now become more challenging,” Langpap said.

“The next milestone is the completion of design for the UV (ultraviolet) and advanced water treatment systems by April 2017,” said district engineer Paul Prestia.

Subsequent deadlines are June 2017, for design of the brine concentration system, and 2018, for the beginning of construction, Prestia said.

As for satisfying the judge’s demands for complying with CEQA, Sanitation District officials said it was too early to determine how long that would take.

If the district misses any of the benchmarks between now and the 2019 deadline, the Regional Water Quality Control Board can find it out of compliance and issue fines, a cost ultimately passed on to ratepayers.

The last time the district fell out of compliance was November 2012. The water quality board named the district a polluter and fined it about a quarter of a million dollars.

[email protected]

661-287-5527

on Twitter @jamesarthurholt

← Back to 2016

About this record

How it was held, read and classified

Record details

Morris ID
153829
System
Morris section CMS (/section/…/article/… and /archives/…)
Reading copy
signalscv.com
Chosen by: only copy held. On this copy: words 436 (e-mail addresses counted as one token); reader comments 5 (counted, not reproduced here); images 1.
Extracted by
section_cms:articlebody_span
signal-extract/0.15 (2026-11-16)

Other copies

Held
None. The holding has this article from one host only.

How it was classified

Label
clearly-local
Judgment
A machine’s (recorded as machine), kept as one so it can be revisited.
Classifier
signal-localclass/0.7 (2026-11-12)
Local signals
  • url:section_36_local
  • byline:staff_marker [[address]]
  • text:valley_names [2 distinct/4 mentions: Santa Clarita, SCV]
National signals
none fired
Scores
local 8, national 0