If you think traffic in the Santa Clarita Valley is bad now, just wait a few months. The California Department of Transportation is preparing to shut most of the ramps and lanes along Interstate 5 between Valencia Boulevard and Castaic at various times over the next four years.
It’s all part of a five-year reconstruction project that started a year ago with the widening of the Valencia Boulevard overpass. The Valencia overpass had to be widened— and McBean Parkway had to be re-striped — because the roads will need to handle more traffic when the real freeway construction starts.
And what’s behind the freeway construction? Two things. The Magic Mountain Parkway overpass was damaged in the earthquake of Jan. 17, 1994, as was a bridge over the river just to the north of it. They’ve remained in use only because there is no alternative. Fifty-five million vehicles use the overpasses every year— actually more, because that’s a 10-year-old figure.
The other reason for the freeway improvements is that the thoroughfare will need to accommodate more traffic if and when The Newhall Land and Farming Co. gets the go-ahead to build its 21, 600-home Newhall Ranch project. That’s why Newhall Land paid the total cost of the Valencia overpass widening, the McBean re-striping , and much of the cost of the rest of the I-5 construction— which gets underway next month.
How is it all supposed to work? That was the topic of a meeting Monday with Caltrans officials, who appear to have been woefully neglectful in the communication department the last couple of years. Not only do many adjacent businesses not know what’s going on; other state officials say they’ve been left out of the loop.
“It’s easy (for Caltrans) to build it... but we’re the ones that have to answer all the questions,” said CHP Captain Brian Kilmer, who expressed his concerns about the eleventh-hour notification from the highway department.
Business people who rely on the Rye Canyon Road on-ramp for customers were told they’ll have to get by without that traffic. The news didn’t come with any explanation of how that was to happen. One business is still under construction there— and its owner says he would not have built there, had he known.
It wasn’t clear Wednesday exactly how or when Caltrans alerted them to the details of the roadwork— if at all, prior to Monday. Caltrans officials said they didn’t disclose the details earlier because the plans were still being finalized and they didn’t want to give out bad information.
Now some businesses are threatening to sue Caltrans to block construction, potentially delaying some freeway improvements which— despite the pain they’ll cause— really must be performed, because we can’t live with quake-damaged bridges forever.
It will be a painful process when freeway traffic starts using city streets at various intervals over the next four years. The pain could be eased a little if Caltrans were a bit more thorough in letting folks know exactly what’s going on.