A 70-acre site in Sloan Canyon is the most viable property for a future high school in the Castaic area, according to a report issued by the staff of the William S. Hart Union High School District.
The recommendation is being presented to the governing board Wednesday and comes after the district received input from consultants, the Department of Education, the public and district staff on three potential sites in the Castaic area including land at the corner of Hasley and Del Valle and in the NorthLake development.
This is not a surprise to Steve Boldvich, president of the Castaic Area Town Council, whose members have written a letter to the school district in opposition to the site. Boldvich contends the Hart district is not listening to Castaic residents.
“The community is not behind this site,” said Boldvich, who represents the Hasley/Sloan area. “While they are totally behind a high school in the Castaic area, I’ve talked to quite a few residents, and we will continue to fight for an appropriate site on the northern end of town.”
Controversy arose this year when the Santa Clarita Valley Facilities Foundation, the development arm of the high school district, entered into an escrow agreement for the Sloan/Hasley areas without input from the community or Town Council.
Several meetings have been held with the community since then, with the majority in attendance asking the district to consider alternative sites.
In September, the district toured potential sites with members of the Castaic Area Town Council and was directed by the school board to evaluate three potential sites to determine the feasibility of each location.
According to the report, the Hasley/Del Valle site, which can be acquired at no cost to the district, has several environmental concerns including an earthquake fault and adjacent oil wells. To make the site viable for a high school, the district would also have to purchase an additional 12 to 14 acres.
The NorthLake property would be too costly for the district, the report states, as the district would be required to pay for much of the infrastructure including utilities and an access road to have it ready by 2005.
While the report states the Hasley/Sloan site meets all criteria, Castaic residents contend a high school will negatively impact their community, citing an increase in traffic, jeopardy to the safety of children on residential streets and destroying the rural quality of life.
Hart board member Steve Sturgeon said the district needs to plan ahead for new school sites and delays in the site selection may affect funding.
“It takes years from acquisition of the land to the opening of the school. The state has stringent rules and regulations with regards to school sites and their acceptability,” he said. “Our goal is to do what is best for the kids and based on growth, we need more classrooms.”
The Hart District Facility Master Plan calls for the construction of a high school in the Castaic area to help reduce overcrowding, particularly at Valencia High School, where more than 3,000 students are enrolled.
It is estimated that high school enrollment in the Castaic area will exceed 2,000 students by the year 2007. High school students in Castaic and Val Verde are currently attending Valencia High.
Grading is complete on the Golden Valley High School site and bids are now being accepted for the school construction. Grading will be complete on West Ranch High School in April.
The facilities foundation has extended the escrow on the Sloan/Hasley site several times. On Wednesday, the district will consider a possible lease on the property.